Maestron-Property-Solutions's logo

How Long Does A Kitchen Remodel Take In The Houston Metropolitan Area?

Habib's Image

Habib Othman

CEO · Licensed Texas PE

Last Updated -
home kitchen renovation work

If you live in the Houston Metro Area and you are planning on remodeling your kitchen, I am sure you are curious about the usual kitchen remodel timeline here. In fact, this is the first question we are asked at MPS by both homeowners and realtors. 

Now, to be honest, kitchen renovation in Houston can take anywhere from a few weeks to months. Here, a small renovation with no layout will take less time while a full renovation with  new plumbing, electrical work, walls, custom cabinets will take much longer. 

The construction part itself takes between 6 and 12 weeks. But the entire remodeling process starting from planning and moving to material selection and final walkthrough can take realistically 2-6 months, or even more.

I have explained how long does a kitchen remodel take exactly for every kitchen size and remodeling type based on our own projects. Also, I have shared some tips that you can follow to avoid common delays.

So, let’s get into it. 

Key takeaways

  • A small, mostly cosmetic kitchen remodeling will take between 2-4 weeks.
  • A standard kitchen remodeling without layout change will take between 6-10 weeks.
  • A large kitchen remodeling project with plumbing, electrical, or layout changes will take between 8-12.
  • A major gut remodel with structural changes can take between 10-16 weeks.
  • These estimates are for construction only, and planning, material ordering, permits, etc., can take longer.  

How long does a kitchen remodel take exactly in Houston?

For starters, there isn’t a standard kitchen remodel timeline that applies to all homes in the Houston area. The exact timeline depends on the size of your kitchen and the extent of renovation you are doing,

However, to give you a rough idea, here’s how long kitchen renovation takes: 

Type of kitchen remodelingApproximate timeline
Small/cosmetic only update2-4 weeks
Standard same-layout remodeling6-10 weeks
Larger remodel with plumbing/electrical changes8-12 weeks
Major/full-gut remodel10-16 weeks

Again, these are not guaranteed timelines, and the exact time it takes to remodel your kitchen can be different. 

Nevertheless, if you just replace kitchen cabinets, countertops, backsplash and lighting, you can expect the 6-10 week timeline. And if your project involves moving the walls, sink, range, and electrical lines, your timeline can extend to 8-12 weeks. 

Note: These estimates are for active construction phase only

The kitchen remodel timelines I mentioned above account only the active construction phase.

You will also spend time planning the renovation, redesigning your kitchen, choosing cabinets, countertops and appliances, and securing permits. This can take anywhere between 2-6 months depending on how big your project is. 

For instance, if you are moving or modifying interior walls, altering ceiling framing, or expanding your kitchen size, you’ll need a Building Permit for residential remodeling. This alone will take between 2-6 weeks to secure. 

Ready To Improve Your Property?

Tell us about your project and we’ll create renovation, repair, and restoration solutions designed around your goals.

blog cta image

How long does the entire kitchen renovation process take?

While the kitchen renovation timeline for active construction gives you a realistic idea about how long a Houston property contractor might take to renovate, the overall process takes much longer.

Overall, here’s how long should a kitchen remodel take from start to finish: 

StageApproximate timeline
Planning and design2-8 weeks
Material procurement2-12 weeks
Permits, if needed2-6 weeks
Demolition2-5 days
Plumbing or electrical work1-3 weeks
Cabinets and other finishes2-4 weeks
Countertops installation1-3 weeks
Final work & punch listUp-to 2 weeks

Pro tip: Don’t add every timeline in this list together as a lot of stages work together. 

Here’s what happens during every stage of kitchen renovation process:

1. Planning and design

This is the first step in kitchen remodeling. Here, you plan each and every remodel detail, including layout, cabinets, countertops, appliances, flooring, lighting, plumbing fixtures and finishes. 

This stage can take a couple of weeks for a simple project and longer when there are a lot of design decisions involved. 

2. Ordering materials

This is where you order kitchen materials such as cabinets, countertops, appliances, etc. And this is also the stage which sometimes stretches your kitchen remodeling timeline while some materials are readily available, others need to be manufactured and delivered. 

3. Demolition

Demotional only takes a few days. Here, kitchen cabinets, countertops, etc., are removed. Also, if you are changing kitchen layout, walls, plumbing lines, etc., can be demolished too.

4. Plumbing, electrical and other rough work

This stage of kitchen renovation is straightforward if you are not changing the kitchen layout. 

But if you’re moving the sink, dishwasher, range or other major appliances, additional plumbing, electrical or gas work will be needed. And this will stretch the timeline, more so if hidden problems are found. 

5. Cabinets, countertops and finishes

At this stage, cabinets are installed and leveled, and countertops are measured, fabricated, and installed. This can take 1-4 weeks in total if cabinet and countertop installation is being done side-by-side. 

6. Final walkthrough 

This is the stage in the kitchen renovation process where contractors finish everything that is remaining, including adjusting cabinet doors, touching up paint, completing trim, installing hardware, etc. You can expect this to take another 2 weeks. 

What can make a kitchen remodel timeline longer in Houston?

There are several things that can affect your kitchen renovation schedule, including: 

1. Changing the kitchen layout

Changing layout is the biggest reason kitchen renovation timelines exceed. That’s because moving plumbing, electrical circuits, gas lines or walls creates more work than replacing items in their existing locations.

2. Material lead times

Sometimes custom cabinets, countertops, and kitchen appliances can take a lot longer than expected to be delivered. This can increase the timeline by another few weeks. 

3. Permits and inspections

Houston Metro is not one single permitting jurisdiction. A project inside the City of Houston follows a different permitting process from one in another municipality or in an unincorporated part of Harris County. And depending on the jurisdiction, the permitting timeline can be longer. 

For instance, if your project is in Harris County and you are moving walls or changing layout, you will need a permit from the Office of the County Engineer. This will take 2 to 3 weeks, which is less than that in the City of Houston. 

4. Hidden problems

A remodel can uncover water damage, outdated wiring, plumbing problems or framing issues that need to be addressed before the project can continue. This can increase the timeline by weeks or even a month. 

5. Changes during construction

If you change a cabinet selection after ordering, it can affect delivery, installation, and everything that depends on that installation. This also goes for countertops, appliances, plumbing fixtures, and other materials.

Bonus: Here’s what to do before kitchen renovation starts

What to doWhy
Finalize major decisionsChoose cabinets, appliances, countertops, and fixtures early.
Confirm material lead timesKnow when important materials will actually arrive.
Understand the scopeClearly define layout, plumbing, electrical, walls, and other changes.
Ask about permitsConfirm which permits are required for your specific project.
Plan for time without your kitchenSet up a temporary space for meals, coffee, refrigeration, and cleanup.

FAQs about kitchen remodel timeline

How long does a kitchen remodel take in the Houston area?

A small kitchen update takes around 2-4 weeks of construction, while a standard remodel can take 6-10 weeks. Larger projects involving layout, plumbing, electrical or structural changes can take 8-12 weeks or longer. 

How long does it take to remodel a small kitchen?

A small kitchen can be remodeled in 2-4 weeks if the work is mostly cosmetic and materials are readily available. 

However, a small kitchen involving major layout, plumbing, electrical or structural changes can take much longer. 

How long does a full kitchen remodel take?

A full kitchen remodel can take roughly 10-16 weeks or longer for active construction, depending on the amount of demolition, layout changes, structural work, plumbing, electrical work, materials and inspections involved. 

Can a kitchen remodel be completed in 4 weeks?

It can be possible for a small project with limited scope. However, four weeks is not a realistic expectation for every kitchen remodel. 

How much does a kitchen remodel cost?

The cost of kitchen remodeling depends on the size of your kitchen and the extent of remodel you are undertaking.

For instance, the average cost of a 10×10 kitchen remodel is anywhere between $15,000 and $50,000, depending on scope of work. 

Ready To Improve Your Property?

Tell us about your project and we’ll create renovation, repair, and restoration solutions designed around your goals.

blog cta image

Wrapping it up

I am sure that you now have a good idea about how long does a kitchen remodel take in Houston.

To put it simply, if it is a straightforward project, you are looking at a few weeks of active construction. But it is a more involved project, 8-12 weeks of construction is standard. 

Also, the complete kitchen renovation can take several months if you take into account planning, material ordering, and permitting.

Got more questions or want to renovate your kitchen?

You can get in touch with us!

At Maestro Property Solutions, we are seasoned kitchen renovation experts with 50+ years of combined expertise and decades of boots on the ground experience. We will plan your kitchen renovation exactly around your budget and deliver a kitchen exactly as you’ve imagined. 

✖

Tell Us About Your Project

No spam. No sales calls. Just a straight conversation about your property.